Aug 16, 2011

Day 98 (16th Aug 2011) - Plasterboard

Plasterboard is on today! But i don't think it's finished yet. When I drove by late this afternoon, the workers were still working in the house.

I will take some photos when it's done.

Aug 13, 2011

Day 95 (13th Aug 2011) - Scaffolding is off

Scaffolding is removed and now we can see our house clearly! There are damages under the eaves maybe caused by the scaffolding removing progress. I will call my liason to check that out on Monday, I think BB will replace them.

SS told us the small things that need to modified from last inspection have already been done. Furthermore, the plaster boards will be installed next week and then the carpenters will start~ We officially move to the Fix Stage, whoohoo~


Hot water system's base:

Cleaned bricks~

Aug 9, 2011

Day 91 (9th Aug 2011) - Lockup Inspection

We had our Lockup stage inspection (Pre-plaster inspection) this afternoon.

This time we hire another inspector to do the inspection. This inspector has many years experience in house inspection and he's very famous in some building forums. When I called him, he suggested that we should have the pre-plaster inspection instead of the lockup inspection. Some electrician drill holes through timber inappropriately that might damaging the frame works. So we hold the inspection until our SS told us the electricity, plumbing n insulation are done. 

This inspector is very detail concerned. It took one and half hour to complete the inspection. He told us BB did a very good job and he's amazed. BB uses good quality timber for the frames, every room's size is correct, BB does many detail works while other builders don't care about small things. In conclusion, our inspector rated our house's quality as in top 10% based on all his past inspections. I just wanna to thank all the workers and our lovely lovely SS!! Our SS communicated with the inspector this time and walked with him all the way through. It's much easier for us cuz they can understand each other's 'construction related words'. Nothing major problems were found, just some smalls things need to be modified. Yah~~~

I took some photos while inspecting. 





Aug 7, 2011

Day 89 (7th Aug 2011) - Cladding n Eaves are Painted

Cladding and eaves are painted this week. I was worried about the Colorbond Surfmist is too white with Hawthorn bricks. When I saw it today, what a relief!! Nice bright white matches well with my bricks!!! Love it!!!

Furthermore, top half of the brick wall is washed and cleaned, again, love Hawthorn so much~

My SS told me the plumbing and electricity are done, how quick they are! However I can not go inside my house without BB's permission, I will take some photos when we have the Lockup inspection next week.

So far so good~



Aug 3, 2011

Day 85 (3rd Aug 2011) - Cladding is Done

Cladding is done but it hasn't been painted yet. I guess the painter will paint it with eaves together.



Some wading birds nearby~

Jul 29, 2011

Day 80 (29th July 2011) - Antenna is on

Bricking is done! Antenna is on, silver n shiny~ Little chimney (dunno what's it called, lolz) is on as well. I'm told that cladding will be on next week and then they will remove the scaffold to tile the roof on alfresco.

PS, our liason left BB, pity, she's very good at her job, reachable, fast response and very familiar with all the details. A new liason is on our case now.



Jul 23, 2011

Day 73 (22nd July 2011) - Roof finished

Roof is done and some bricklayers are working on site! Looks like the solar panels is on. I took the pic from one side.


Today I found a pond about 100m from our house, and there are many ducks inside, beautiful view~